SCOPE

Handed over ready to live in

A house isn’t ready when the renovation ends; there are things that still have to go into it. We run the furniture, the appliances and the curtains from one hand too — because the handover date is usually set not by the building work but by the lead times on these items.

The handover date is set by imported furniture and motorised curtains, not by the building work.

Motorised curtainCABLE IN THE WALLSeatingMADE TO MEASUREBuilt-in appliancesTIES DOWN THE KITCHENAppliancesLEAD TIME 8–16 WEEKSTHE HOUSE IS USABLE AT HANDOVERCurtain measurements are taken once the window frames are in;the motor decision comes before the electrical plan.

WHAT’S INCLUDED

What we do under this heading

All of the following sit inside the same contract. You can take an item out if you want to — but taking it out is your decision, not a limit on what we can do.

Furniture and textiles

  • Seating
  • Dining table and chairs
  • Beds
  • Rugs
  • Pictures and mirrors
  • Accessories

Appliances

  • Oven
  • Hob
  • Extractor hood
  • Dishwasher
  • Fridge
  • Washer and dryer
  • Built-in appliance solutions

Curtains and solar control

  • Made-to-measure curtains and blinds
  • Watern blinds
  • Blackout curtains
  • Sheers
  • Motorised curtain systems
  • Pelmets and concealed tracks

Handover

  • Styling and setting the house up before handover
  • Professional photography

WORTH NOTING

Where the work gets difficult on this item

We say these things at the quotation stage, not afterwards. We don’t like surprises.

  • The lead time sets the handover. On imported furniture and motorised curtains the lead time runs to 8–16 weeks. If these items aren’t ordered at the design stage, the house finishes and then waits for its furniture.
  • Motorised curtains need wiring. The cable for a motorised system runs inside the wall. If the decision isn’t made before the electrical plan, either the cable shows or the system falls back to a battery solution.
  • The window frames finish before the curtains are measured. Curtain measurements are taken after the windows and frames are installed. A measurement taken early means a curtain that is short or long.
  • Built-in appliance dimensions tie down the kitchen. Appliance models have to be chosen before the kitchen units are made. An oven changed later changes the unit carcase.

THE DECISION CALENDAR

Which decision you make, and when

Every line becomes an annex to the contract. If a date slips, the work behind it slips too.

  1. Design stageChoosing appliances and furnitureThe dimensions tie down the kitchen and cabinetry production.
  2. End of designLong lead-time ordersImported furniture and motorised curtains, 8–16 weeks.
  3. After the frames are installedCurtain measurementThe firm measurement is taken once the windows are finished.
  4. Before handoverStyling and photographyThe house is handed over in a usable state.
SHORT-TERM LETTING

We have a separate package for letting: hard-wearing materials, a multi-bed layout and a “ready to live in” handover that includes crockery and cutlery.